As the operator of a combustion plant (medium-sized combustion plant, gas turbine and internal combustion engine plant), you are obliged to notify the competent authority of the intended operation before commissioning. Existing combustion plants that were put into operation before 20 December 2018 had to be notified to the competent authority by 1 December 2023.
The responsibilities in the area of immission control are regulated in the Immission Control Competence Ordinance of the state of Baden-Württemberg.
In most cases, the competent authority for installations that fall under the scope of the 44th BImSchV is the local lower immission control authority, i.e
A different responsibility applies in the following cases, for example in the case of companies that are subject to the European Industrial Emissions Directive, the Hazardous Incident Ordinance or mining law:
Departments 5, Environment of the respective locally responsible regional councils are the competent immission control authorities for business premises on which
exists or is to be constructed.
Department 9, State Office for Geology, Raw Materials and Mining of the Freiburg Regional Council is also the state-wide competent immission control authority for
Please ensure that you submit the notification to the immission control authority responsible for your combustion plant.
The notification obligation applies to
The notification must contain the information specified in Annex 1 of the 44th BImSchV.
The notification must be submitted electronically to the competent authority.
The authority checks the notification formally and for completeness.
If the notification is incomplete, the competent authority will notify you.
Once the formal check has been passed, the competent authority enters the installation in the register of installations and informs you of the registration.
The notification must be submitted before commissioning a new system. The operation of an existing installation must be notified by 1 December 2023.
There are no costs.
Please make sure that you submit the notification to the immission control authority responsible for your combustion plant.
Vierundvierzigste Verordnung zur Durchführung des Bundes-Immissionsschutzgesetzes
VERORDNUNG (EG) Nr. 1893/2006 DES EUROPÄISCHEN PARLAMENTS UND DES RATES vom 20. Dezember 2006
Vierte Verordnung zur Durchführung des Bundes-Immissionsschutzgesetzes
Gesetz zur Ordnung des Wasserhaushalts
Dreizehnte Verordnung zur Druchführung des Bundes-Immissionsschutzgesetzes
machine generated, based on the German release by: Umweltministerium Baden-Württemberg, 27.06.2024
Stadt Kuppenheim
Friedensplatz
76456 Kuppenheim
Telefon: 07222/9462-0
Telefax: 07222/9462-150
stadt@kuppenheim.de