Serviceportal–Baden-Württemberg
Nachfolgend finden Sie die Verfahrensbeschreibungen der Angebote des Serviceportals BW.
Nachfolgend finden Sie die Verfahrensbeschreibungen der Angebote des Serviceportals BW.
If you apply for planning permission using the simplified procedure, you will receive authorisation faster and more cost-effectively.
The competent authority checks less than in other procedures.
As the building owner, you are responsible for ensuring that the public lawn Regulations that apply in thennot be examined in the standardised building permit procedureebe complied with. In individual cases, you must apply for a deviationsor exemption from these Regulations. In the event of a violation, the building authority can stop the construction or have what has already been built demolished. The building permit applied foreauthorisation can be revoked due to arbreach of requirements that are not subject to the simplified procedurerthe simplified procedure.
The building permit expires automaticallyif you do notrwithin three years of the authorisation being granted or if the construction work begins after the authorisation has been grantedeperiod has been interrupted for one year. Thisthese Three-yearsperiod can be extended.
the lower building authority
Depending on the location of the building project, the lower building authority is
The simplified building permit procedure is available for building projects that are not special buildings and for which the notification procedure has not been opened or is not desired by the client. In detail:
and
The building application with all the necessary building documents and the completed survey form for the statistics on construction activity is submitted electronically by the building owner to the responsible building authority via the online service provided by the authority (in of the rule ViBa-BW). Deviations, exceptions and exemptions must be applied for separately.
The building authority checks within ten working days whether the building documents are complete and which other offices and departments need to be involved in the process. If the building documents are incomplete, the building authority will advise which additions are required. As soon as the building application and the building documents are complete, the expected date of the decision is communicated.
The building authority examines the building application exclusively with regard to
It consults the municipality, if it is not itself the building authority, and those bodies whose area of responsibility is affected. This is, for example, the monument protection authority if it is a cultural monument or the project has an impact on a neighbouring registered cultural monument.
If deviations, exceptions or exemptions are applied for that also serve to protect the neighbour, the municipality will notify the owners of the properties adjacent to the building plot (adjoining owners) within five working days of receiving the complete building documents at the instigation of the building authority. This gives them the opportunity to raise objections to the building project within four weeks.
Once all comments have been received and the building application has been reviewed, the decision is made: The building permit is granted, granted only with certain conditions and requirements or the building application is rejected.
Construction of the project may only begin once the building permit has been granted and the building permit, the so-called "red dot", has been issued.
A building inspection under public law only takes place if the building authority has expressly ordered this.
Note: Firing systems may only be put into operation once the authorised district chimney sweep has certified that they are fire-safe and that the combustion gases are safely discharged.
none
The building documents marked with * can be submitted later. If necessary, the building authority can request further documents in individual cases or dispense with individual building documents. The documents must be submitted in archivable Portable Document Format (pdf/A) via the transmission channel specified by the building authority.
The costs are based on the rates specified in the respective statutes or legal ordinances.
Depends on your individual case and, above all, which authorities need to be involved. The procedure usually takes between one month and four months.
If you have any questions, please contact your architect, your housing association or the responsible office.
Machine generated, based on the German release by: Ministerium für Landesentwicklung und Wohnen Baden-Württemberg, 03.04.2025
Stadt Kuppenheim
Friedensplatz
76456 Kuppenheim
Telefon: 07222/9462-0
Telefax: 07222/9462-150
stadt@kuppenheim.de